St Helens Esplanade

Sewer Pump Station Upgrade

July 2017 - May 2019     TasWater
  • Upgrading the Esplanade Sewage Pumping Station, by way of decommissioning the existing pump stations, and providing a new pump station and emergency storage

  • Decommissioning and demolition of existing sewer pump station at Esplanade

  • Earthworks and concrete works: two new pump stations of 4m in diameter

  • Pipework: Approximately 2km of DN250 PN16 PE100 sewerage pipelines from Jason Street pump station to Esplanade pump station and to Sewer Treatment Plant.

  • Electrical works including new main switch board and instrumentation.

  • Sewer connections.