St Helens Esplanade
Sewer Pump Station Upgrade
July 2017 - May 2019 TasWater
-
Upgrading the Esplanade Sewage Pumping Station, by way of decommissioning the existing pump stations, and providing a new pump station and emergency storage
-
Decommissioning and demolition of existing sewer pump station at Esplanade
-
Earthworks and concrete works: two new pump stations of 4m in diameter
-
Pipework: Approximately 2km of DN250 PN16 PE100 sewerage pipelines from Jason Street pump station to Esplanade pump station and to Sewer Treatment Plant.
-
Electrical works including new main switch board and instrumentation.
-
Sewer connections.