Bathurst Street, Hobart Watermain Renewal

May 2019 - July 2019     TasWater

Renew the watermain with new DN150 DICL class PN35, installation of new DN150 inline isolation valves, new fire hydrants, service connections (night works)

  • Length: 200m of DN150 DICL

  • Budget: $290k

  • Construction date: From June 2019 – July 2019)

  • Construction method: Open trenching